Three Valley Gap – Installing Nine Wyssen Tower
A joint effort between Canadian Rescue Systems, Tangiers and Wyssen Canada. The Three Valley Gap construction project involves accessing very extreme terrain and installing 9 Wyssen towers.
Canmore Sink Hole
A very high hazard construction site. Tangiers along with Geobrugg and Encora Engineering performed a design build to cap a vertical mine shaft that was continually collapsing. The area needed to be closed down while the solution was being installed. The Hazard was mitigated in 5 days and rehabilitated into a park and pathway.
Utah State
Tangiers was asked to install the first Wyssen Avalanche tower in the USA. The area was an environmentally sensitive area at 10,500 feet. A powerful Vietnam era Huey helicopter was needed for the install due to the high altitude.